This 65,200 sq. ft. combined cycle plant was built in eastern Ohio. It was done in two phases. Phase 1 consisted of the installation and operation of three 160 megawatt gas fired combustion turbines, a 1,000 kW emergency generator, and a 290 kW emergency fire pump. Phase 2 included a 14-cell wet cooling tower, a gas-fired auxiliary boiler, a 100 kW back-up diesel generator, and a small 290 kW firewater pump.